🔄 Change Orders User Guide
Field Entry Portal, Change Order Creation & Management
Overview
The Change Orders module manages scope changes during construction projects. It provides a field-friendly entry portal for creating change orders on-site and a management dashboard for tracking approvals and costs. Access change orders under Project Management → Change Orders in the navigation menu.
Change Order Dashboard
Navigation: Project Management → Change Orders
Features
- Change Order List: View all change orders across projects
- Status Tracking: Draft, Submitted, Under Review, Approved, Rejected
- Cost Impact Summary: Total change order value and impact on project budget
- Rate Settings: Configure billing rates for change order labor
Dashboard Metrics
| Metric |
Description |
| Total COs |
Number of change orders across all projects |
| Pending Approval |
COs awaiting review and approval |
| Approved Value |
Total dollar value of approved changes |
| Budget Impact |
Net change to project budget |
Field Entry Portal
Navigation: Project Management → Change Orders (Field Entry Portal)
Mobile-Friendly Entry
The Field Entry Portal is designed for on-site use with mobile devices:
- Simplified Forms: Quick entry fields optimized for mobile
- Photo Capture: Attach photos of the work requiring a change
- GPS Location: Automatically tag the location of the change
- Offline Support: Create entries without internet and sync later
Creating a Change Order
- Navigate to the Change Orders page
- Click "+ New Change Order" or "Field Entry"
- Fill in change order details:
- Project: Select the associated project
- Title: Brief description of the change (e.g., "Add electrical outlets – 2nd floor east")
- Description: Detailed explanation of the scope change
- Reason: Why the change is needed (Owner Request, Design Change, Unforeseen Condition, Code Requirement)
- Cost Estimate: Estimated additional cost
- Time Impact: Additional days required
- Supporting Documents: Photos, sketches, specs
- Submit the change order
Change Order Fields
| Field |
Description |
| CO Number |
Auto-generated reference number |
| Project |
Associated construction project |
| Title |
Short description of the change |
| Description |
Detailed scope of the change |
| Reason Code |
Category of why the change is needed |
| Estimated Cost |
Dollar value of the change |
| Time Impact |
Schedule impact in days |
| Priority |
Low, Medium, High, Critical |
| Status |
Draft, Submitted, Under Review, Approved, Rejected |
Change Order Approval Workflow
Draft → Submitted → Under Review → Approved / Rejected
↓
Budget Updated
↓
Work Authorized
- Field Worker creates the change order (Draft)
- Project Manager reviews and submits for approval
- Owner/Client reviews the cost and scope impact
- Approval or Rejection with notes
- If approved, the project budget is automatically updated
- Blockchain record created for the change (if project is on-chain)
Rate Settings
Navigation: Available from the Change Orders dashboard
- Configure standard billing rates for labor categories
- Set markup percentages for materials and equipment
- Define overhead and profit margins for change orders
- Rates are used to auto-calculate change order costs
Viewing Change Order Details
Click any change order to see the full details view:
- Complete Cost Breakdown: Labor, materials, equipment, markup
- Timeline Impact: Original vs. revised schedule
- Approval History: Who reviewed and when
- Supporting Documents: Photos and attached files
- Blockchain Record: Immutable record of the change (if applicable)
Tips & Best Practices
- Document changes immediately in the field — don't wait until you're back in the office
- Attach photos to provide visual evidence of the changed condition
- Get approval before starting changed work whenever possible
- Track all cost changes even small ones — they add up
Last Updated: February 2026